Jobs#2418 — Hollis Residence

Hollis Residence — new asphalt driveway

Job #2418 · 4212 Chestnut Ct, Pasadena MD 21122 · Crew A
On site now — 2h 47m on the clock
Justin, Mike and Luis clocked in at 7:00 AM. Six of eight required photos captured. Balance of $4,200 is collectable on site.
In progress

Scope & spec

Area
1,850
sq ft measured
Depth
2"
compacted
Mix
9.5mm Superpave
Genstar — Millersville
Tonnage
22.4
tons ordered
Base
14 tons CR-6
Tack coat
18 gal
Edging
Hand-raked, 2 sides
Access
Gate code 4417
Client asked that the crew keep off the lawn on the left side — new sod put down in June. Downspout at the garage corner drains across the pad; grade away from it.

Job photos

6 of 8 requiredAdd
Before — north
Before — south
Base compacted
Tack coat down
First lift
Rolling
Still required before this job can be invoiced: two after-shots (full driveway from street, and the transition at the garage apron).

Labor & time

PersonRoleInOutHoursCost
Justin BittnerForeman7:00 AM2.78$139
Mike RowanOperator7:00 AM2.78$100
Luis MarreroLaborer7:12 AM2.58$77
Running labor cost $316 · estimated at $780 for the full dayCosting

Activity

Sixth photo uploaded by Luis
Today, 9:38 AM
Crew clocked in on site
Today, 7:00 AM · Justin, Mike, Luis
22.4 tons picked up from Genstar Millersville
Today, 6:30 AM · ticket #88214 attached
Deposit of $1,400 paid by card
Aug 19 · Visa ending 4417
Estimate EST-0331 approved and signed
Aug 19 · signed online by Dana Hollis
Estimate sent
Aug 17 · opened twice
Lead created from website form
Aug 15 · "driveway is cracking, want it redone"

Money

Contract value$5,600.00
Deposit paid Aug 19−$1,400.00
Balance due$4,200
Card on file · Visa 4417

Job cost so far

Hot mix — 22.4 t @ $118$2,643
CR-6 base — 14 t @ $32$448
Tack coat — 18 gal$74
Labor (running)$316
Cost to date$3,481
Projected margin38%
Quoted at 53% — labor is running long

Client

DH
Dana Hollis
Residential · first job
410-555-0188
dana.hollis@example.com
4212 Chestnut Ct, Pasadena
Found you on GoogleOpen client

After this job

Once this is marked complete, the driveway enters the seal-coat recall list with a due date of August 2028 — roughly $680 of work at today's rate.