Jobs#2418 — Hollis Residence
Hollis Residence — new asphalt driveway
Job #2418 · 4212 Chestnut Ct, Pasadena MD 21122 · Crew A
On site now — 2h 47m on the clock
Justin, Mike and Luis clocked in at 7:00 AM. Six of eight required photos captured. Balance of $4,200 is collectable on site.
Scope & spec
Area
1,850
sq ft measured
Depth
2"
compacted
Mix
9.5mm Superpave
Genstar — Millersville
Tonnage
22.4
tons ordered
Base
14 tons CR-6
Tack coat
18 gal
Edging
Hand-raked, 2 sides
Access
Gate code 4417
Client asked that the crew keep off the lawn on the left side — new sod put down in June. Downspout at the garage corner drains across the pad; grade away from it.
Job photos
6 of 8 requiredAdd
Before — north
Before — south
Base compacted
Tack coat down
First lift
Rolling
Still required before this job can be invoiced: two after-shots (full driveway from street, and the transition at the garage apron).
Labor & time
| Person | Role | In | Out | Hours | Cost |
|---|---|---|---|---|---|
| Justin Bittner | Foreman | 7:00 AM | — | 2.78 | $139 |
| Mike Rowan | Operator | 7:00 AM | — | 2.78 | $100 |
| Luis Marrero | Laborer | 7:12 AM | — | 2.58 | $77 |
Running labor cost $316 · estimated at $780 for the full dayCosting
Activity
Sixth photo uploaded by Luis
Today, 9:38 AM
Crew clocked in on site
Today, 7:00 AM · Justin, Mike, Luis
22.4 tons picked up from Genstar Millersville
Today, 6:30 AM · ticket #88214 attached
Deposit of $1,400 paid by card
Aug 19 · Visa ending 4417
Estimate EST-0331 approved and signed
Aug 19 · signed online by Dana Hollis
Estimate sent
Aug 17 · opened twice
Lead created from website form
Aug 15 · "driveway is cracking, want it redone"
Money
Contract value$5,600.00
Deposit paid Aug 19−$1,400.00
Balance due$4,200
Card on file · Visa 4417
Job cost so far
Hot mix — 22.4 t @ $118$2,643
CR-6 base — 14 t @ $32$448
Tack coat — 18 gal$74
Labor (running)$316
Cost to date$3,481
Projected margin38%
Quoted at 53% — labor is running long
Client
DH
Dana Hollis
Residential · first job
410-555-0188
dana.hollis@example.com
4212 Chestnut Ct, Pasadena
Found you on GoogleOpen client
After this job
Once this is marked complete, the driveway enters the seal-coat recall list with a due date of August 2028 — roughly $680 of work at today's rate.