EstimatesEST-0345 — Alvarez Residence

Estimate builder

EST-0345 · Alvarez Residence · 30 Ben Oaks Dr, Severna Park · Draft

Measure & calculate

Paving-specific
1,850sq ft
2in
9.5mm Superpave
CR-6, 4"
5%
53%
Hot mix required
22.4
tons · 1,850 × 0.167 ft × 145 lb/ft³
Material cost
$2,643
22.4 t @ $118/ton
Suggested price
$5,600
53% gross margin
Also pulled in automatically: 14 tons CR-6 base ($448), 18 gal tack coat ($74), and a half-day roller rental if the job runs past 4 hours. Prices come from the price book and were last updated from the Genstar quote on Aug 12.
Change the depth or area and every line below re-pricesPrice book

Line items

DescriptionQtyUnitRateTotal
Tear out existing asphalt driveway
Haul off and dispose, 1,850 sq ft
1,850sq ft$0.55$1,018
Grade and compact subgrade
Laser grade, slope away from garage
1,850sq ft$0.32$592
CR-6 crusher run base, 4" compacted
14 tons delivered
14ton$68.00$952
Tack coat
18 gallons
18gal$8.50$153
Hot mix asphalt, 9.5mm, 2" compacted
22.4 tons — calculated above
22.4ton$118.00$2,643
Roll and hand-work edges
Two sides hand-raked
1job$242.00$242
Subtotal$5,600.00
Deposit required (25%)$1,400.00
Total$5,600

Terms shown to the client

25% on signature
Due on completion
Estimate is valid for 30 days. Client signs online; signature converts this into a scheduled job automatically.

Margin check

Price to client$5,600
Material$3,165
Labor (est. 9 crew-hours)$780
Equipment & haul$310
Gross profit$1,345
53% gross margin — above your 45% floor.

Weather window

If signed today, the first open day that clears your paving rules is Monday, September 1. Friday and Saturday are out at 70–85% rain.
Needs dry and 50°+Schedule

Client

RA
Rafael Alvarez
Residential · referral
Referred by the Mercer job on Bayard Rd. Asked twice about financing.