Crew
5 on the payroll · 2 crews out today · 64 hours booked this week
A
Crew A — paving
On siteTruck 1 + paver · left the yard 6:42a · 2 stops today · 22.4 tons
Day is 46% done — running about 14 minutes behind.
JB
Justin Bittner
Foreman · on the clock 2h 47m
$50/hr
MR
Mike Rowan
Paver operator · on the clock 2h 47m
$36/hr
LM
Luis Marrero
Laborer · on the clock 2h 35m
$30/hr
Loaded labor rate $116/hrSee their phone view
B
Crew B — repairs & seal
On siteTruck 2 + patch trailer · left the yard 7:15a · 2 stops today
Day is 22% done — on time, and has room for two more stops.
TD
Tony DiSalvo
Lead · on the clock 1h 52m
$38/hr
DK
Dave Krall
Laborer · on the clock 1h 52m
$28/hr
Loaded labor rate $66/hrFill from recall list
Hours this week
| Person | Role | Mon | Tue | Wed | Thu | Fri | Total | Cost |
|---|---|---|---|---|---|---|---|---|
| Justin Bittner | Foreman | 9.5 | 10.0 | 2.8 | — | — | 22.3 | $1,115 |
| Mike Rowan | Operator | 9.5 | 10.0 | 2.8 | — | — | 22.3 | $803 |
| Luis Marrero | Laborer | 9.0 | 9.5 | 2.6 | — | — | 21.1 | $633 |
| Tony DiSalvo | Lead | 8.0 | 7.5 | 1.9 | — | — | 17.4 | $661 |
| Dave Krall | Laborer | 8.0 | 7.5 | 1.9 | — | — | 17.4 | $487 |
100.5 hours · $3,699 labor cost so far this weekLabor vs. revenue
Equipment
| Asset | Assigned | Status | Next service |
|---|---|---|---|
| Truck 1 — F-550 dump | Crew A | In service | Oil at 94,200 mi (in 1,100) |
| Paver — LeeBoy 8515 | Crew A | In service | Screed plates — check monthly |
| Roller — Bomag BW120 | Crew A | In service | Hydraulic service Oct |
| Truck 2 — F-350 | Crew B | In service | Brakes at next inspection |
| Patch trailer + tack tank | Crew B | Tack pump leaking | Fix before Friday |
| Skid steer — rented | As needed | Off rent | $310/day when needed |